The conventional chiller installed at a high-rise multifamily condominium in Queens County, New York City had run the course of its useful life and it was time for a replacement. However, many challenges existed – such as limited space, budget and time – to achieve a successful installation of the new chiller. The HIGHMARK team analyzed the situation and knew the perfect solution: the Aermec WWM Modular Chiller.
| Application | High-rise multifamily residential building |
| Location | Queens County, New York City |
| Project type | Mechanical, Electrical, Engineering |
| Technologies |
Aermec WWM Modular Chillers Space-efficient equipment Energy-efficient building management |
| Project size |
15 stories 59 residential units 3 commercial units 89,253 sq. ft. |
| Completion | 2019 |
The Aermec WWM Modular Chiller 0500 (30 tons) was identified as the best technology for this project. The HIGHMARK team had worked with Aermec to reinvent the WWM to be tailored to the exact needs of New York City’s buildings. Consequently, eight WWM units were incorporated to overcome the specific challenges of the building.
The reinvented Aermec WWM Modular Chiller was the perfect solution for the job for the following reasons:
The Aermec WWM 30-ton modular chiller was the perfect solution for the challenges faced by this multifamily residential building. The WWM was able to overcome the many issues faced and achieve the following results: